Construction Update

Construction Photos | Construction Cam Archives



March 19
, 2001
Construction started under sunny skies on Monday 3/19/01
The schedule currently calls for the following activities to take place next week (3/26-3/30):
Footings formwork and rebar placement in preparation for concrete placement.
Placement of underslab piping and conduits prior to placement of concrete.
Excavation and placement of the various underground concrete tanks.
Electrical service tie-in to the existing IMT power service for supply to the new building.

April 16, 2001
All Building Footings are in place along with the Alternative Waste Storage & Bio-Solids Tanks.
Under Footing Drain, Feed Lines and Electrical Sleeves installed.
Upcoming Construction Activities:

Masonry Perimeter & Interior Walls
Installation of the Re-Use Water Storage Tank
Installation of the Influent Pump Station
Site Related Pressure Piping & Electrical Conduits



April 30, 2001

Ongoing & Scheduled Construction Activities:
Completion of the Masonry Walls (North), Remaining Interior/Exterior Walls Complete
Damproofing of Exterior Walls below grade prior to backfilling
Backfill and Compaction of Subgrade @ Wetlands and Tank & Utility Trenches
Formwork in preparation of placement of Slab on Grade @ Wetlands and Tank & Utility Trenches
Installation of the Influent Pump Station
Site Related Pressure Piping & Electrical Conduits
May 15th, Greenhouse Structure Delivery to Site


May 29, 2001

Ongoing & Scheduled Construction Activities:
Erection of the Aluminum Framed Greenhouse
Installation of System Pumps and Controls in the Various External Tanks
Installation of Housekeeping Pads in preparation for setting the Process Tanks
Installation of Supports for all Process Piping and Electrical Systems
Waterproofing within the Wetlands in preparation for installation of the Gabions and Filtration Media


July 3, 2001


Updated 5/29/01